Medium-Voltage Feeder Protection Settings: A Step-by-Step Guide to ANSI 50/51, 50N/51N, 67 and 67N

A worked IEC/IEEE guide to phase and earth overcurrent pickup, inverse curves, CTI, directional polarisation, CT performance and commissioning.

Feeder protection settings must sit inside a feasible window: above maximum legitimate load, unbalance, inrush and transient quantities, yet below the minimum fault that must be detected—and coordinated in time with downstream clearing and upstream backup. ANSI 50/51, 50N/51N, 67 and 67N are not independent menu entries; they share CT/VT performance, topology, grounding and breaker time.

This step-by-step method develops phase and earth overcurrent settings for MV feeders, including directional polarisation, inverse curves, tolerances, distributed generation, worked illustrative calculations and commissioning tests. It is not a settings template: use the approved short-circuit/coordination study and exact relay manual.

Executive rules

  • Calculate maximum load/emergency/motor-start and minimum/maximum phase/earth faults for every topology.
  • Convert all quantities on one documented primary/secondary basis with actual CT/VT ratios.
  • Set pickup from both sides: security above nonfault current and dependability below minimum fault.
  • Coordinate total clearing time, not relay operate time alone; include tolerances, breaker and arc time.
  • Use 50 only where a current threshold truly separates the protected close-in zone from downstream through faults/inrush.
  • Earth-fault settings follow system grounding and residual-measurement method, not phase-fault rules divided by a constant.
  • 67/67N require verified current/voltage polarity, forward definition and valid polarising quantity under weak/close-in faults.
  • Test boundaries and dynamic waveforms, then validate load phasors before enabling directional/high-speed elements.

1. Standards and nomenclature

ReferenceApplication
IEC 60255-151:2009Minimum functional/performance requirements for over/under-current protection, including time characteristics and influencing factors
IEC 60255-1:2022Common relay/scheme requirements and tests
IEEE C37.112-2018Active standard defining inverse-time characteristic equations/allowances, including varying current
IEEE C37.2-2022Device function numbers/acronyms and contact designations
IEC 61869-1:2023 / IEC 61869-2:2012Instrument-transformer/CT performance framework
Relay manufacturerExact curve equation/constants, measurement algorithm, directional polarisation, tolerances and logic
  • 50: instantaneous or definite-time phase overcurrent stage commonly applied without intentional inverse delay.
  • 51: time-delayed phase overcurrent, often inverse-time.
  • 50N/51N: neutral/residual earth overcurrent; suffix naming varies (N/G) and input source must be stated.
  • 67/67N: directional phase/earth overcurrent supervised by direction.

2. Required study data

  • one-line and normal/contingency/maintenance/generator/island topologies;
  • source/transformer/cable/line/motor/generator impedances and X/R;
  • maximum demand, emergency load, overload, cold-load pickup and motor starting profiles;
  • minimum and maximum three-phase, phase-phase and earth faults by location;
  • grounding transformer/NGR/reactor/arc-suppression-coil and system charging current;
  • downstream fuses/relays/contactors and upstream backup characteristics;
  • CT ratio/class/burden/saturation and residual connection/CBCT data;
  • VT ratio/fuse/selection and directional polarising availability;
  • breaker opening/arcing/total clearing tolerance and interrupting duty;
  • equipment cable/transformer/motor thermal/damage and arc-flash limits.

3. Establish a calculation basis

For CT ratio CTR = Iprimary,rated/Isecondary,rated:

Isecondary = Iprimary/CTR and Iprimary = Isecondary × CTR.

Record whether relay settings are amperes secondary, amperes primary or multiples of nominal current. For residual from three phase CTs, the relay input measures vector sum; it is not automatically equal to an independently measured neutral/CBCT input during CT saturation/mismatch. Check relay nominal 1 A/5 A configuration and active settings group.

4. Phase 51 pickup window

Define a security floor and dependability ceiling:

Ipickup,51 > Kload × Imaximum legitimate, while Ipickup,51 < Iminimum required fault/Kdep.

  • Kload covers measurement/CT error, load forecast, acceptable overload, unbalance and reset margin.
  • Kdep covers fault-study uncertainty, arc resistance, source outage and relay/CT error.
  • Check cable/transformer/motor continuous and emergency ratings; pickup must not authorise thermal overload beyond equipment design.
  • Check motor starting/cold-load profile against inverse-time operating accumulation/reset, not pickup alone.
  • If the feasible window disappears, improve sensors/protection/topology; do not force a setting.

5. Choose the 51 characteristic

For common IEC inverse curves, a generic form is t = TMS × k / [(I/Is)α − 1]; constants k and α define standard, very or extremely inverse families. IEEE C37.112 uses its defined equation/allowances. Use the exact relay implementation, reset/integration and any definite minimum time.

Curve tendencyTypical coordination valueCheck
Standard/normal inverseBroad relay-relay coordinationMay be slow at high multiples
Very inverseUseful where fault current reduces with distance and downstream devices have inverse behaviourLoad/start and low-fault time
Extremely inverseCan coordinate with fuse/thermal I²t-like characteristicsHigh-current time, CT saturation and equipment duty
Definite timePredictable grading in constrained networksSlower upstream clearing and step count

6. Coordination time interval

At each common fault current, require:

tupstream,total − tdownstream,total ≥ CTI.

  • downstream relay/fuse operate and tolerance;
  • downstream breaker opening/arcing/clearing and tolerance;
  • upstream relay negative tolerance/overtravel/reset behaviour;
  • CT saturation and measurement/filter delays;
  • auxiliary/interposing/output and communication time;
  • coordination safety margin/project criterion.

Plot total-clearing curves/bands, not a single nominal point. Check minimum and maximum source, close-in and remote fault, multiple downstream devices, tie/coupler states and evolving/fault-current-changing conditions.

7. Phase 50 high-set element

  • Find maximum external/downstream through-fault current seen by the relay including topology/DER and study uncertainty.
  • Add margin for CT transient response, relay overshoot/tolerance and asymmetrical current representation.
  • Find minimum close-in internal fault in the weakest source state.
  • Check transformer energisation, motor start/reacceleration, capacitor switching and load transfer.
  • Set pickup only if a robust gap exists; otherwise use intentional delay, directional/zone logic or disable 50.
  • Check CT saturation does not cause underreach for high internal faults or false residual.
  • Coordinate high-set with downstream current-limiting fuses/contactors and breaker interrupting/close-latch duty.

8. 50N/51N earth-fault inputs

MeasurementStrengthConstraint
Residual of phase CTsNo separate sensor; handles higher earth currentsCT mismatch/saturation/lead errors limit sensitive pickup
Core-balance CTHigh sensitivity and direct 3I0Aperture, cable screen/earth routing, range and saturation
Neutral CTMeasures transformer/generator grounding pathZone/source specificity, ratio/polarity and parallel return paths
  • Set above maximum healthy residual: load unbalance, charging current contribution, CT error, harmonics/transients and measurement noise.
  • Set below minimum earth fault after fault resistance and weakest source/grounding path.
  • Coordinate with NGR/grounding-transformer thermal rating and downstream earth protection.
  • In low-resistance grounded systems, definite/inverse 51N may coordinate; 50N needs selectivity/through-fault margin.
  • In isolated/resonant systems, current magnitude alone may be inadequate; use sensitive directional/admittance/wattmetric/intermittent earth-fault methods.

9. Directional phase overcurrent 67

  • Define forward current direction relative to the protected feeder and CT P1/P2.
  • Select line/phase voltage polarisation, cross-polarisation, memory voltage or negative-sequence method supported by the relay.
  • Set characteristic angle from positive-sequence/source/line impedance and relay convention—not by copying another vendor’s angle.
  • Check close-in three-phase fault voltage collapse and memory duration.
  • Check reverse faults, parallel feeders, bus coupler, transformer phase shift and embedded generation.
  • Use minimum polarising voltage/current supervision and define behaviour on VT fuse failure.
  • Test torque/directional boundary at minimum current/voltage and frequency/phase-error extremes.

10. Directional earth overcurrent 67N

67N compares residual/zero-sequence current with a polarising quantity such as residual voltage, negative-sequence voltage/current or another vendor-specific method. Sign conventions for 3I0, 3U0, active/reactive residual power and characteristic angle differ—document the relay equation and primary forward-fault phasor.

  • Verify phase CT residual/CBCT/neutral CT polarity and VT broken-delta/residual polarity.
  • Calculate network charging-current direction/magnitude for healthy and faulted feeders.
  • Use grounding method to choose wattmetric, varmetric, admittance, conductance or negative-sequence direction.
  • Check intermittent/restriking faults and harmonics in resonant-earthed networks.
  • Set minimum residual voltage/current and directional sector with measurement/tuning errors.
  • Test forward/reverse fault at multiple resistance, inception angle and coil detuning states.

11. Worked illustrative phase example

Illustrative only. An 11 kV feeder has 630 A maximum legitimate load, CT 800/1 A, minimum remote phase fault 2.4 kA, maximum downstream through fault 4.2 kA and minimum close-in fault 7.5 kA. A downstream device clears a 3.6 kA fault in 0.35 s; required grading margin is 0.30 s.

  • Select 51 pickup 1.00 A secondary = 800 A primary after confirming 800/630 = 1.27 covers approved load/overload margin and 2.4 kA gives multiple M = 3.0.
  • For an illustrative IEC very-inverse equation t = 13.5×TMS/(M−1), at 3.6 kA M = 4.5.
  • Required upstream relay/clearing target must include its breaker; simplifying here to relay target 0.65 s gives TMS ≥ 0.65×3.5/13.5 = 0.169. Choose next supported value 0.18, then redo with actual breaker/tolerance bands.
  • At 2.4 kA, ideal relay time = 13.5×0.18/(3−1) ≈ 1.22 s; check equipment damage and upstream backup.
  • A tentative 50 pickup 5.5 kA lies above 4.2 kA and below 7.5 kA, but accept only after asymmetry/CT/relay/study margins, inrush and minimum internal-fault coverage demonstrate a robust gap.

Do not use the simplified target calculation as a final setting. Plot manufacturer curves and tolerance/clearing bands at all fault locations/topologies and check CT transient performance.

12. Illustrative resistance-grounded earth window

Assume an NGR limits solid earth fault to about 400 A, minimum studied fault including resistance/source tolerance is 320 A, and maximum healthy/transient residual at the selected CBCT is 20 A. A tentative sensitive pickup such as 60 A primary lies above healthy residual and below minimum fault. Finalise only after CBCT accuracy/saturation, cable screen routing, harmonic/transient, NGR thermal time and downstream/upstream coordination. Phase-CT residual may require a higher security floor.

13. Special operating scenarios

  • embedded generation/reverse power changes phase-fault direction and fault contribution;
  • island operation reduces minimum fault and changes frequency/voltage polarisation;
  • bus coupler changes source impedance and direction;
  • transformer parallel/one-out changes through-fault and earth zero-sequence path;
  • motor contribution decays with time, affecting instantaneous and BF current criteria;
  • arc resistance/high-impedance faults reduce current below traditional pickup;
  • automatic transfer/reclose requires cold-load/motor residual and settings-group coordination;
  • maintenance grounding/VT selection/CT ratio changes require controlled settings group or outage.

14. CT performance checks

  • ratio chosen for load resolution and maximum fault input range;
  • class/ALF or knee point/transient specification suited to protection application;
  • hot lead plus relay/test-block burden;
  • asymmetrical fault/X/R and remanence where relevant;
  • saturation effect on 50 underreach, 51 delay, residual spill and directional phasor;
  • relay waveform algorithm/CT saturation detector performance;
  • CBCT aperture, conductor placement, screen/earth return and low-current calibration;
  • 1 A/5 A hardware/configuration and safe shorting/test facilities.

15. Verification workflow

  1. Peer-review study model, cases, grounding and CT/VT data.
  2. Export relay-native settings report and compare primary/secondary conversions.
  3. Plot phase/earth TCCs with tolerance and equipment-damage/starting curves.
  4. Secondary-inject pickup/dropout and operate time at boundary/multiple points.
  5. Dynamic-test inrush, motor start, CT saturation, directional close/reverse and intermittent earth cases.
  6. Verify trip/lockout/BF/AR/ATS/SCADA logic and settings-group selection.
  7. Primary-inject or prove CT/CBCT ratio/polarity and complete trip path where practical.
  8. Check live load phase sequence, current/voltage polarity, power direction and healthy residual.
  9. Test VT fuse/lost polarisation, DC/network/time failure and fail-safe response.
  10. Archive calculation, settings/checksum, test files, waveforms and final margins.

16. Frequent mistakes

MistakeConsequenceCorrection
Pickup = 125% of nameplateActual emergency load/min fault ignoredTwo-sided feasible window
One short-circuit caseWeak/strong/DER topology missedAll operating states
Relay times coordinatedBreaker/arc/tolerance absentTotal clearing bands
50 always enabledDownstream fault/inrush overtripRequire robust current gap
Earth pickup copied from phaseGrounding/charging/CT mismatchGrounding-specific study
67 angle copied between vendorsConvention/polarity reversalEquation/phasor verification
Steady injection onlyTransient/security defects latentDynamic and failure tests

17. Settings-release checklist

  • All topologies/load/start/fault/grounding cases approved?
  • CT/VT ratios, polarity, burden and saturation validated?
  • Phase/earth pickup feasible windows demonstrated?
  • Curve equation/constants and reset behaviour exact?
  • Total-clearing coordination/tolerance/damage limits plotted?
  • 50/50N robust selectivity gap demonstrated or disabled/delayed?
  • 67/67N forward convention/polarisation/fuse-failure secure?
  • DER/island/coupler/settings-group logic covered?
  • Breaker time/DC and BF escalation included?
  • Dynamic/boundary/failure tests passed?
  • Live-load phasors/residual direction verified?
  • Calculation, native settings/checksum and as-built evidence controlled?

References and further reading

Engineering note: Worked values are illustrative and deliberately incomplete. Final settings require the approved study, exact relay curves/tolerances and verified breaker/CT/VT performance.

LearnSwitchgear

Search the engineering library