Secondary injection can prove relay settings, measurement, logic and outputs with high precision—but only inside its declared test boundary. Injecting directly at an IED terminal does not verify CT/VT ratio, field wiring or primary polarity; stopping at a relay trip LED does not verify the breaker trip path.
This guide builds a rigorous MV switchgear relay FAT under IEC 60255. It covers configuration freeze, parameter- and system-based tests, current/voltage/binary injection, pickup/dropout/timing, curves, directional/differential/voltage/frequency functions, scheme logic, GOOSE/Sampled Values, tolerances, breaker operation, event records, change control and restoration.
Executive conclusions
- Freeze and read back the installed settings, logic, I/O, firmware, SCL and active setting group before test.
- Define the injection boundary and excluded equipment on every report.
- Use parameter-based tests to verify individual elements and system-based scenarios to verify interaction/logic; neither alone covers everything.
- Test pickup, dropout/reset, operate time, curve shape, direction, restraint and blocking as applicable—not one point per function.
- Separate relay algorithm time, output-contact time, breaker opening time and total scheme time.
- Check CT/VT primary-secondary scaling, frequency, phase sequence and zero-sequence calculation before judging elements.
- Use the actual trip matrix and verify each output through lockout/interposing/DC coil/breaker where FAT scope permits.
- For IEC 61850, test normal GOOSE/SV plus quality, test/simulation flags, subscription loss, time and network failure.
- Apply declared relay and test-set tolerances with an agreed conformity rule; do not compare displayed rounded values as exact.
- Remove every force, test mode, output block and temporary setting, then read back the as-left file/checksum.
1. Test boundaries
| Injection point | Included | Excluded |
|---|---|---|
| IED analogue terminal | Relay input/algorithm/logic/output | CT/VT, test block and field wiring |
| Panel test block | Test block-to-IED wiring plus relay | Primary CT/VT transformation |
| Merging-unit SV input | Digital data/IED algorithm | Sensor/MU analogue chain if simulated |
| Physical relay output to breaker | Relay output, DC path, coil, breaker/feedback | Protection analogue primary chain unless separately tested |
| GOOSE message simulation | Subscriber logic/output path | Real publisher input/logic unless end-to-end |
Combine staged tests for diagnosis with end-to-end tests for confidence. Label every result so a simulated internal bit is not mistaken for primary-chain proof.
1A. Risk-based coverage strategy
Do not copy every possible setting into hundreds of low-value points, and do not sample away critical logic. Build coverage by requirement and risk:
- one or more boundary points for every enabled measuring element;
- multiple points across every inverse, differential/bias, distance or directional characteristic used for coordination;
- every trip output, breaker/coil channel and lockout destination;
- every permissive, block, setting-group, autoreclose and breaker-failure branch;
- all CT/VT/phase/residual input mappings and normal/degraded measurement states;
- each communication-based trip/interlock and its loss/bad-quality response;
- representative repeated points to confirm phase consistency and timing scatter;
- full testing of design variants; sample identical feeders only with proven configuration identity and failure escalation.
A requirements traceability matrix should show why each test exists and which untested combinations are covered by design identity or prior evidence. “Automated 100% pass” is meaningless if the template never exercised a disabled high-set or wrong output mapping.
2. Inputs and configuration freeze
- approved protection study and settings schedule;
- relay native settings and human-readable comparison report;
- firmware/hardware/modules and manufacturer manuals;
- CT/VT ratios, cores, polarity and wiring diagrams;
- trip/cause-effect matrix and interlocking philosophy;
- binary I/O, LEDs, HMI, alarm/SOE and disturbance-record settings;
- active setting group and group-change logic;
- SCD/CID, GOOSE, Sampled Values, report and time configuration;
- test template/equations/tolerances and test-set calibration;
- open deviations, disabled elements and expected future site settings.
Read back the configuration from the installed IED and calculate a checksum. Compare values including hidden/default logic and scaling—not only protection pickups visible on a summary sheet.
3. Safety and test facilities
- Primary equipment de-energised/controlled for breaker operations.
- CT side shorted before relay side is opened; CT short removed only after reconnection.
- VT source isolated before secondary voltage injection to prevent backfeed.
- Test-set neutral/earth and panel PE arranged to avoid loops/shorts.
- Voltage/current outputs off before lead changes.
- Trip outputs blocked only under a controlled register when breaker operation is not intended.
- Remote/intertrip/GOOSE outputs isolated from adjacent live equipment.
- Breaker operation count, mechanism state and moving-part boundary controlled.
- Every temporary link/force/test mode independently cleared at completion.
4. Test-set configuration
- nominal secondary current/voltage (1 A or 5 A; 100/110 V arrangements);
- primary-secondary scaling and √3/residual conventions;
- system frequency and phase rotation;
- current/voltage source ranges, compliance and output burden;
- binary input wet/dry thresholds and debounce;
- binary output rating/polarity and DC wetting source;
- time reference/sample rate and trigger definition;
- GOOSE/SV interface, VLAN/APPID/MAC/dataset and test/simulation flags;
- template/XRIO/model version and manufacturer tolerance data;
- test-set/software/firmware serial/calibration.
OMICRON’s current CMC 500 official information describes modular multi-phase current/voltage sources and parameter-based Test Universe plus system-based RelaySimTest approaches, including GOOSE, MMS and Sampled Values. Test capability does not validate a template automatically; review every mapping and tolerance.
5. Metering and plausibility first
- Inject balanced three-phase nominal quantities.
- Verify relay RMS magnitudes, angles, frequency, phase sequence and primary display.
- Inject one phase at a time to prove channel mapping.
- Verify residual/negative/zero-sequence quantities from controlled unbalance.
- Check power direction, P/Q sign and phase-earth/phase-phase voltage conventions.
- Verify HMI/SCADA values, units, scaling and deadbands.
- Resolve metering/scaling/polarity errors before protection timing tests.
6. Pickup, dropout and reset
- Hold non-tested polarising/restraint quantities at defined values.
- Ramp or step the operating quantity from below pickup at an approved rate.
- Record pickup from element state, not final trip if intentional delay exists.
- Increase safely above pickup, then decrease to record dropout/reset.
- Calculate dropout/pickup ratio where relevant.
- Repeat phases and directional quadrants/setting groups as required.
- Apply relay accuracy plus test-set uncertainty to the acceptance decision.
A very slow ramp can interact with filtering/memory; a coarse step can overstate pickup precision. Use the relay/test-module method and preserve step size/ramp rate.
7. Definite and inverse-time tests
- Test below pickup/no trip, just above pickup and representative high multiples.
- For definite time, measure element and output contact separately where needed.
- For inverse curves, test several current multiples spanning coordination range.
- Use the exact IEC/IEEE/manufacturer curve family, time multiplier/dial and minimum time.
- Account for intentional start/operate/reset and breaker/output delay.
- Verify high-set instantaneous/short-delay transitions.
- Check curve crossing/coordination points relevant to the protection study.
- Preserve calculated expected time and tolerance source.
8. Directional elements
- Verify voltage/current polarising channels and phase rotation.
- Test forward and reverse faults at equal magnitudes.
- Sweep operating angle around characteristic boundaries.
- Test minimum polarising voltage/current and memory polarisation where used.
- Test close-in/zero-voltage behaviour and directional earth-fault residual quantities.
- Verify reverse direction blocks output and generates expected start/status.
- Check CT/VT polarity and P/Q sign before changing relay characteristic.
9. Differential and REF tests
- Confirm CT ratios, vector/phase compensation and protected-zone mapping.
- Inject equal through current to prove stability/restraint.
- Inject internal differential current to prove pickup/operate.
- Test slope/bias characteristic at multiple restraint levels.
- Test high-set/unrestrained stage and harmonic/other restraint if applicable.
- For REF, verify neutral/phase CT polarity and stabilising principle.
- Test CT saturation/open-circuit supervision logic by approved secondary simulation.
- Record differential and restraint quantities displayed by relay.
10. Voltage, frequency and thermal functions
- 27/59 phase-earth/phase-phase pickup, delay, hysteresis and fuse-failure blocking.
- 59N/residual voltage scaling and earth-fault/VTS discrimination.
- 81U/O frequency pickup/delay and voltage supervision.
- 81R/ROCOF ramp rate, window/filter and islanding logic.
- 46 negative-sequence current calculation and delay.
- 49 thermal model heating/cooling, preload, reset and alarm/trip.
- Loss-of-load/undercurrent/power functions where used.
- Setting-group or motor start/restart logic interactions.
11. Logic and scheme tests
- breaker failure: current/no-current supervision, retrip, timer and correct backup outputs;
- autoreclose: shots, dead/reclaim time, block/lockout, synch-check and unsuccessful close;
- 86 lockout: trip, latch, reset permissive and close block;
- synch-check: voltage, angle, frequency slip, dead/live conditions and timeout;
- intertrip/permissive: send/receive, channel supervision and failure state;
- bus transfer/selector logic: source availability, interlocks and no unintended paralleling;
- trip matrix: every element to correct coil/breaker/alarm;
- setting-group logic: source, priority, indication and change under load.
12. Output path and breaker operation
- Inject the actual protection quantity at the panel test block where possible.
- Observe element pickup/operate, logic and selected relay output.
- Measure output/interposing/86 and trip-coil voltage/current.
- Verify correct breaker opens and other breakers remain unchanged.
- Confirm 52a/52b, TCS, lockout and breaker-failure current reset.
- Verify alarm/target/HMI/SCADA/SOE/disturbance record.
- Record relay time, output time, breaker time and total end-to-end time separately.
13. IEC 61850 GOOSE and Sampled Values
- Verify SCD/CID revision and publisher/subscriber mapping.
- Inject/subscribe to exact dataset members and quality attributes.
- Test test/simulation mode so test messages cannot operate normal plant unintentionally.
- Measure end-to-end application response, not Ethernet frame latency alone.
- Open one network path and verify PRP/HSR/design redundancy.
- Test lost/stale/bad-quality subscription alarm/fail-safe logic.
- For SV, verify sample rate, synchronisation quality, channel scaling and phase mapping.
- Check PTP/time failure and event/disturbance timestamps.
14. Acceptance and uncertainty
A test point’s acceptance band should combine the relay’s declared accuracy/tolerance, algorithm/curve tolerance, test-set uncertainty and project decision rule. Do not simply subtract two rounded display values.
- Use expected-value equations from the correct curve/function.
- Document whether tolerances are additive, relative or absolute.
- Choose points with margin from characteristic intersections where practical.
- For boundary tests, use pass/fail pairs on either side rather than one exact threshold.
- Investigate a result near the limit; do not tune settings to make the template green without engineering approval.
- Preserve raw outputs and calculated values.
15. Changes, retest and regression
- Record first failure and active configuration.
- Verify test wiring/template/model before blaming the relay.
- Open a controlled settings/logic/wiring change.
- Assess protection coordination and all dependent outputs/interfaces.
- Download, read back and checksum the revised file.
- Repeat failed point plus boundary/related functions.
- Repeat end-to-end trip, alarms/SOE and GOOSE/SCADA dependencies.
- Keep before/after results and approval.
16. As-left restoration and report
- IED/panel/serial/firmware/settings checksum and active group;
- test boundary/diagram and CT/VT scaling;
- test set/software/template/calibration;
- injected phasors, frequency, binary/GOOSE/SV conditions;
- expected/calculated/actual pickup and timing with tolerance;
- logic/output/breaker/alarm/SOE results;
- raw traces, disturbance files and screenshots with context;
- NCR/change/regression history;
- all outputs unblocked, test/simulation/forces cleared;
- CT/VT blocks, trip circuits and normal SCL/settings restored;
- final read-back/checksum and independent sign-off.
Common mistakes
- Calling relay-terminal injection an end-to-end CT/VT test.
- Testing one point per element.
- Ignoring dropout, direction, restraint and blocking.
- Using wrong CT/VT scaling or phase rotation.
- Stopping at the relay trip LED.
- Combining relay and breaker time without boundaries.
- Trusting a library template without limit review.
- Testing GOOSE normal state only.
- Changing settings to pass without coordination review.
- Leaving output blocks/test modes/forces active.
Official standards and primary references
- IEC 60255-1:2022 — current common requirements for measuring relays/protection equipment.
- IEC 60255-27:2023 — current protection-equipment safety requirements.
- IEC 60255-26:2023 — current EMC requirements for protection equipment.
- IEC 61850-6 consolidated edition, IEC 61850-8-1 consolidated edition and IEC 61850-10:2012+AMD1:2025 — configuration, communication mapping and conformance framework.
- OMICRON CMC 500 official information — current modular parameter/system-based and digital-substation relay-test platform example.
- OMICRON CMC 356 official information — legacy/current-fleet multi-phase relay-test reference, superseded by CMC 500.
Engineering note: The protection study and approved installed settings—not a test library—define intended operation. Secondary injection is strongest when its boundaries and exclusions are explicit. Keep the expected-value calculation, curve equation, tolerance source and raw injection vector with every automated result so a future reviewer can reproduce the decision without the original proprietary template and software.