A neutral grounding resistor (NGR) deliberately limits
single-line-to-ground fault current. If the resistor or its connection
fails open, the system can become effectively ungrounded and its
earth-fault protection may become blind. If it is shorted or bypassed,
fault current can rise far above the intended value. Protecting the
feeder is therefore only half the job: the grounding path itself must be
continuously supervised.
Design rule: treat the NGR, neutral conductor,
grounding transformer, sensing transformer, CT and monitoring relay as
one protection system. A healthy resistor in an open conductor is not a
healthy grounding system.
This article explains high- and low-resistance grounding, equipment
ratings, relay functions, setting calculations, trip philosophy and
commissioning tests for medium-voltage systems.
1. What resistance
grounding changes
In a three-phase system, the neutral-to-earth voltage during a ground
fault drives current through the neutral grounding impedance. With a
predominantly resistive path and a bolted ground fault, the approximate
resistor current is:
IG ≈ VLN / RNGR
where:
- VLN = VLL / √3;
- RNGR is the hot resistance of the
complete grounding resistor at the relevant temperature.
The resistor’s instantaneous power during the fault is
approximately:
P = IG²R =
VLNIG
and the thermal energy for a constant-current duration
t is:
E = Pt
These equations are useful checks. Final ratings must include
tolerance, temperature coefficient, system-voltage range,
grounding-transformer impedance, source impedance and the applicable
equipment standard.
Low-resistance grounding
Low-resistance grounding (LRG) commonly permits tens or hundreds of
amperes so conventional relays can locate and clear the fault
selectively. The NGR usually has a short-time rating coordinated with
primary and backup clearing. Continued operation with the first ground
fault is generally not the objective.
High-resistance grounding
High-resistance grounding (HRG) limits current to a low value, often
in the ampere range. Where the total charging current and
transient-overvoltage criteria permit, the system may alarm on the first
ground fault and continue operating long enough for controlled fault
location. A second ground fault on another phase is a phase-to-phase
fault through earth and must be prevented by operating discipline and
rapid location.
The labels “high” and “low” resistance do not determine a universal
current threshold. The system study, regulatory practice and operating
philosophy define the application.
2.
Direct neutral and grounding-transformer arrangements
If the transformer or generator winding has an accessible neutral,
the NGR can be connected directly between neutral and earth. The
resistor insulation is then selected for neutral voltage and system
conditions.
If the system has no accessible neutral, a zig-zag or wye-delta
grounding transformer can create one. In that case the design must
include:
- grounding-transformer continuous and short-time current/thermal
duty; - zero-sequence impedance and its effect on fault current;
- NGR referred through any transformer ratio;
- transformer phase and earth-fault protection;
- CT locations that distinguish NGR current from transformer internal
faults; - neutral displacement voltage measurement;
- switching and interlocking so the bus is never energised without its
grounding source.
Where two incomers or bus sections can be paralleled, the grounding
paths may also become parallel. Two identical NGRs in service can
approximately double total fault current. The switching matrix must
define which neutral earthing device is connected in every bus
configuration.
3. Equipment data required
The protection designer should obtain:
- maximum and minimum system voltage and frequency;
- transformer/generator winding connection and neutral
availability; - desired ground-fault current and permitted duration;
- calculated system phase-to-earth charging current;
- minimum arcing-fault current to be detected;
- NGR cold and hot resistance, tolerance and temperature
coefficient; - continuous or time rating, duty cycle and allowable repeat
duty; - voltage insulation level, enclosure, creepage and environmental
rating; - grounding-transformer ratio, vector group and zero-sequence
impedance; - neutral CT ratio, class, thermal rating and secondary burden;
- sensing-transformer or coupling-device ratio and permissible test
voltage; - cable and conductor thermal withstand for the complete neutral
path; - upstream and downstream earth-fault settings and clearing
times; - permitted response to the first HRG fault and to an open NGR.
The specified NGR current must be sufficient for stable system
behaviour and dependable detection, but low enough to control damage and
arc energy. In HRG applications, the selected resistive current is
normally assessed against the system’s total capacitive charging
current; use a validated study, not a nameplate guess.
4. Failure modes of the
grounding path
| Failure or abnormal condition | Consequence | Detection method | Typical response |
|---|---|---|---|
| NGR element open | System becomes ungrounded; fault current path and protection sensitivity are lost |
Continuous resistance/continuity monitor | Urgent alarm; trip or controlled shutdown per philosophy |
| Broken neutral or earth lead | Same practical result as open resistor | Monitor the entire conductor loop, not only the element | Urgent alarm/interlock |
| NGR partially open or wrong tap | Ground-fault current lower than design | Resistance measurement with alarm limits | Alarm and maintenance |
| NGR shorted or bypassed | Ground-fault current exceeds design | Low-resistance limit, neutral-current plausibility, inspection | Trip or de-energise promptly |
| Grounding transformer unavailable | Bus has no defined neutral | Breaker/disconnector status plus electrical supervision | Block bus energisation or trip |
| NGR overheated | Resistance drifts; element or enclosure can be damaged | Temperature switch/RTD and I²t logic | Alarm/trip according to rating |
| Neutral CT open or failed | Fault current may be missed; dangerous secondary voltage possible |
CT supervision and periodic injection | Alarm; repair urgently |
| Sensing lead open/short | False NGR alarm or hidden failure | Relay self-supervision and lead monitoring | Alarm; apply maintenance policy |
| Sustained first HRG fault | Healthy phases remain elevated to earth; second-fault risk | 59N/neutral current plus fault-location system | Alarm immediately; locate and clear within policy |
5. Why neutral
overcurrent alone is insufficient
A 50N/51N element responds when ground-fault current flows. During
healthy operation, neutral current is close to zero whether the NGR is
intact or completely disconnected. Therefore ordinary neutral
overcurrent cannot prove continuity.
A dedicated NGR monitor can inject or derive a supervision signal and
assess:
- neutral current;
- neutral-to-earth voltage;
- resistance or continuity of the NGR path;
- open or shorted sensing circuits;
- resistor thermal duty;
- the presence of an active ground fault.
The exact method varies. Some relays use an external sensing
transformer and a low-frequency measurement; others calculate resistance
from measured neutral voltage and current. Confirm whether the device
monitors only the resistor element or the complete path through neutral
conductor, terminations and earth connection.
6. Protection and
supervision functions
Neutral overcurrent:
50N/51N or 50G/51G
A neutral CT in the NGR connection directly measures total
ground-fault current from the grounded source. It is often the most
sensitive input for bus and feeder backup. A core-balance CT around the
three phase conductors can be more sensitive for an individual feeder,
because balanced load current cancels magnetically.
Coordinate pickup below the minimum ground-fault current at the end
of the protected zone and above standing unbalance, measurement error
and leakage. Time grading must remain within the NGR’s short-time
rating.
Neutral displacement
voltage: 59N or 64
Neutral-to-ground voltage or residual voltage rises during a ground
fault. It is particularly valuable in HRG systems where current is small
and in systems where feeder residual-current measurements are difficult.
VT fuse-failure or loss-of-potential supervision should block or
restrain voltage-derived functions if their input becomes
unreliable.
Directional earth fault: 67N
In interconnected systems or with multiple grounding sources, current
magnitude alone may not identify the faulted feeder. Directional
earth-fault protection uses residual current and a polarising quantity,
commonly residual voltage. The study must confirm the relay’s angle
convention and the zero-sequence network for every switching state.
Thermal supervision
For a short-time-rated resistor, integrate or model
I²t and coordinate all clearing paths with the
nameplate time. A temperature switch or RTD detects abnormal heating and
failed ventilation where fitted, but does not replace electrical duty
calculation.
Ground-fault pulsing and
location
Some HRG systems pulse the resistor current so portable or fixed
detectors can trace the faulted feeder. Pulsing must stay inside NGR
thermal limits and must not cause misoperation of earth-fault relays or
sensitive loads. Test the complete locate mode before commissioning it
as an operational tool.
7. Worked example A: 6.6 kV
HRG system
Assume a 6.6 kV system is designed for 10 A of resistive ground-fault
current.
Calculate the resistor
VLN = 6,600 / √3 = 3,811 V
RNGR = 3,811 / 10 = 381 Ω
Calculate fault power and
energy
P = 3,811 × 10 = 38.1 kW
For a 10-second short-time duty:
E = 38.1 × 10 = 381 kJ
Suppose the study calculates total phase-to-earth charging current as
2.2 A at nominal frequency. The proposed 10 A resistive current is then
compared with that charging current using the project’s HRG stability
criterion. Voltage tolerance, resistor hot resistance and the
grounding-transformer impedance must still be included before
procurement.
Illustrative relay
philosophy
- Sensitive neutral current or 59N detects the first ground fault and
alarms. - A time-delayed stage initiates a controlled trip if the operator
does not clear the fault within the permitted window. - A high stage trips faster for greater-than-expected current, which
may indicate a bypassed resistor or a second fault. - Dedicated NGR continuity supervision alarms while the system is
healthy and may block energisation after a defined delay.
The actual pickup must be derived from the measured healthy leakage,
charging current, relay resolution and minimum fault resistance to be
detected.
8. Worked example B: 11 kV
LRG system
Assume an 11 kV system requires 400 A ground-fault current for no
more than 10 seconds.
VLN = 11,000 / √3 = 6,351 V
RNGR = 6,351 / 400 = 15.9 Ω
P = 6,351 × 400 = 2.54 MW
E10s = 25.4 MJ
This large short-time power is normal for an LRG nameplate but
illustrates why backup clearing must remain within the duty. If a
neutral CT ratio is 600/1 A, rated NGR current produces:
Isecondary = 400 / 600 = 0.667 A
An illustrative sensitive backup pickup of 0.10 A secondary
corresponds to 60 A primary. It would require checks against standing
residual current, feeder relay grading and the minimum calculated fault.
It is not a generic recommended setting.
9. Setting workflow
- Model every grounding source. Include normal,
split-bus, parallel and emergency-supply configurations. - Calculate charging current. Include cables, motors,
surge capacitors, filters and connected switchgear for each operating
state. - Choose the grounding current. Confirm system
stability, fault-detection sensitivity, equipment damage and arc-energy
objectives. - Rate the equipment. Check hot resistance, voltage
insulation, short-time energy, repeat duty, grounding-transformer duty
and conductors. - Select sensors. Ensure CT ratio and accuracy
resolve the minimum fault but withstand the maximum current; select the
monitoring coupling device to suit system voltage. - Set current and voltage elements. Coordinate feeder
selectivity and backup time with NGR duty. - Set resistance limits. Base open/high and short/low
thresholds on manufacturer tolerances, temperature and measurement
accuracy. - Define first-fault operation. State alarm-only,
pulsing, controlled shutdown or immediate trip; include a maximum
permitted duration. - Design interlocks. Prevent energisation of a bus
without its required grounding transformer/NGR and prevent unintended
parallel paths. - Document testing. Include safe test isolation,
expected primary/secondary values and restoration checks.
10. Example alarm and trip
matrix
| Condition | Alarm | Main breaker/bus incomer | Feeder trip | Lockout/interlock |
|---|---|---|---|---|
| First HRG ground fault | Immediate | Delayed/controlled per policy | Faulted feeder when located | Block reconfiguration that worsens risk |
| LRG ground fault | Yes | Backup only | Selective trip | Per fault type |
| NGR path open | High priority | Trip or controlled shutdown per risk study |
No direct faulted-feeder trip | Block energisation/re-energisation |
| NGR resistance below limit | High priority | Trip or de-energise promptly | No | Block re-energisation |
| Grounding transformer protection | Yes | Trip connected bus source | As required | Lockout |
| NGR thermal limit/temperature high | Yes | Trip before nameplate duty is exceeded |
Faulted feeder should already trip | Block re-energisation until cooled/inspected |
| Monitor or sensing-circuit failure | High priority | Site-specific degraded-mode action | No | Maintenance interlock if required |
11. FAT tests
The factory test should demonstrate:
- entered system voltage, CT and sensing-transformer ratios;
- measured resistance against calibrated standards near alarm
boundaries; - detection of open NGR, shorted NGR and partial-resistance
conditions; - open and shorted sensing leads;
- neutral overcurrent and neutral-voltage pickup/timing;
- correct high-current fast-trip stage;
- thermal/I²t accumulation, reset and memory behaviour;
- pulsing sequence and duty limits where used;
- grounding-transformer and bus interlocks;
- alarm, trip, lockout, SCADA, SOE and disturbance records;
- auxiliary-supply loss and relay self-supervision;
- setting-group behaviour for alternative bus configurations.
12. Site acceptance and
commissioning
Commissioning should prove the physical loop, not just the relay
input:
- inspect resistor elements, links, taps, insulators, clearances and
enclosure bonding; - measure cold resistance with a suitable four-wire method and
correct/compare it to the manufacturer’s reference temperature; - prove the neutral conductor and earth conductor end to end;
- confirm neutral CT ratio, polarity, secondary earth and shorting
facilities; - verify sensing-transformer ratio, insulation and lead
supervision; - inject simulated ground-fault current and neutral voltage with
correct phase relationship; - open a safe test link to prove full-path continuity
supervision; - test high- and low-resistance alarm boundaries using approved
equipment; - trip the actual intended breakers and prove breaker-failure
backup; - verify bus-section and grounding-source interlocks in every
permitted state; - prove pulsing and fault-location equipment if applicable;
- record as-left resistance, ambient temperature, settings, firmware
and test results.
Never disconnect an NGR or open a CT secondary on an energised system
to “prove” an alarm. Use the designed test facilities and an approved
switching procedure.
13. Common mistakes
- Monitoring resistor current but not the integrity of the resistor
path while the system is healthy. - Calculating R = VLL/I instead of using
phase-to-neutral voltage. - Ignoring hot-resistance tolerance and grounding-transformer
impedance. - Selecting NGR current without calculating total system charging
current. - Allowing two NGRs to operate in parallel after bus coupling without
recalculating fault current. - Giving backup earth-fault protection more delay than the NGR
short-time rating permits. - Installing the neutral CT so an unintended parallel earth path
bypasses it. - Treating “first fault alarm” as permission for indefinite HRG
operation. - Testing the monitor at its terminals but not the remote resistor,
conductor and earth connection. - Omitting an interlock that prevents energisation when the grounding
transformer is isolated.
14. Specification checklist
A complete NGR protection specification should state:
- system configurations and available grounding sources;
- target fault current, resistance and tolerance at reference/hot
temperature; - continuous or time rating, duty cycle and insulation level;
- grounding-transformer electrical and thermal data;
- continuous full-path resistance monitoring requirements;
- current, voltage, temperature and I²t functions;
- CT/sensing-transformer data and test isolation;
- HRG first-fault and fault-location operating procedure;
- trip, alarm, lockout and bus interlock matrix;
- communications, disturbance records and SCADA points;
- FAT, SAT and periodic maintenance acceptance limits.
Conclusion
An NGR is an active part of the protection philosophy, not a passive
accessory. Current and neutral-voltage elements detect a ground fault,
while continuous resistance monitoring proves that the intended
ground-current path is available before the fault occurs. Correct
thermal coordination, bus-state interlocking and full-loop commissioning
keep the system inside the assumptions on which every earth-fault
setting depends.
Authoritative
references and further reading
- IEEE
C57.32-2015, Requirements, Terminology, and Test Procedures for Neutral
Grounding Devices - IEEE
3003.1-2019, Recommended Practice for System Grounding of Industrial and
Commercial Power Systems - Littelfuse
SE-330 Neutral-Grounding-Resistor Monitor - Littelfuse
SE-330 datasheet - Bender
LINETRAXX NGRM550 neutral-grounding-resistance monitor
Application note: Grounding philosophy is
system-specific. Confirm the applicable standard edition, utility rules,
safety study, NGR data and exact monitoring-relay manual before
approving design settings or operating procedures.